Ideal Forging update: Road closure could begin on April 1

$
0
0
Ideal Forging Revised Traffic FlowJust days after the updated traffic plan, officials at Weston and Sampson have updated the time frame for demolition. Work is proceeding rapidly, so workers anticipate intermittent road closures of Factory Square/High Street on Wednesday or Thursday to allow safe demolition of the face of 66 High Street. The road would not be closed for the entire day. This may also occur as the water connections at 167 Center are capped, and that is potentially scheduled for next week.